In a contract there may be a number of different times when testing and acceptance may be required. For example:

In an agreement that had major milestones there may be acceptance and test requirements for the completion of the milestone.

For production of an item in volume they may be an acceptance and test of the “first article” produced to ensure that meets the expected requirements.

Prior to the completion of performance there may be a formal acceptance and test required to prove the item meet all the requirements of the agreement.

There can be performance testing that occurs after installation of a software program of piece of capital equipment as part of final acceptance that the item performs as committed.

Whenever there are an acceptance and test requirement several things be included.
1.The party whose work is subject to test and acceptance needs to either delivery the to the other party or provide notice to the other party that it is ready and available for testing and acceptance.
2.The parties should have agreed in advance upon where and how such testing will be performed.
3.For any discrepancies found in testing they parties should have agreed in advance what the impact will be. How long do they have to correct it? Does the test start from the beginning or from some forward point? Who pays the cost of any subsequent tests>
4.The party who has the acceptance and test rights will usually have a time period imposed during which the test and acceptance must be performed. That period should be extended by any discrepancies and retesting required.

Contract managers would be seldom involved in the actual testing and acceptance of the item delivered.Their role is to manage the documentation that surrounds the process and making sure people are aware of times required to complete acceptance and test activity.You retain copies of notices for the test to commence and verify that those meet the requirements of the contract.
You notify individuals that the time period for test and acceptance has commenced and when it needs to be completed by.You manage documentation highlighting and problems or discrepancies and advise the other party of your rights to have the period extended in accordance with the terms of the agreement.Upon final test and acceptance being complete, you provide a formal notice that it has been completed or provide a list of requirements that must be completed with any conditional acceptance.

It is the other party’s responsibility to manage their actions that may be triggered by acceptance such as invoicing for milestone, progress or final payments. The two most important things the contract manager does during this activity is:
1.Ensure that your right to test and accept the item has not lapsed by failing to act within the committed time frame.
2.The contract manager must document when final acceptance has occurred. That is because final acceptance is frequently a trigger for when the warranty period commences.


If you learned from this post, think about how much more you could learn from the book.
The book is only US$24.95 plus shipping. The hot-link to amazon.com is above the date.

6 comments:

  1. The Contract Management Software data added to the system for tracking purposes usually also serves an additional purpose: to facilitate the finding of particular contracts or groups.


    Contract management software
    Agaram infotech

    ReplyDelete
  2. “I love this blog. I don’t know what I’d do without you and your great info! Thank you so much!”

    Contract Management Software

    ReplyDelete
  3. You truly did more than visitors’ expectations. Thank you for rendering these helpful, trusted, edifying and also cool thoughts on the topic.
    Procurement Management Software
    Purchase Management Software
    e Procurement Management Software
    Procurement Tracking Software

    ReplyDelete

  4. Iam so thrilled because of finding your alluring website here.Actually i was searching for Amazon Ad Management.Your blog is so astounding and informative too..Iam very happy to find such a creative blog. Iam also find another one by mistake while am searching the same topicAmazon Master Class.Thank you soo much..

    ReplyDelete
  5. We provide the highest level of quality software products and cms contract management system, asset finance software, floorplan finance, services globally that meet the needs of our customers by maintaining our staff as our principal asset and being responsive to market expectations. Any progressive business demands the right tools to guide innovation and achieve strategic superiority. Having worked with more than 200 finance and leasing companies in over 30 countries, NETSOL Technologies understands the unique operational challenges of todays leasing and finance companies and empowers these organizations to achieve business excellence. Our customized approach and commitment to providing superior quality IT solutions has enabled us to help our clients streamline their business operations and optimize efficiency.

    ReplyDelete